Albuquerque Settles Whistleblower Asbestos Suit
The city paid $250,000 to former Risk Manager Jeannette Chavez, bringing total costs for the Gateway Center asbestos crisis above $1 million.
By Lorenzo Marshall ·

Renovations at the Gateway Center in Albuquerque have generated over $1 million in fines and settlements related to asbestos exposure. In April, the city paid $250,000 to settle a whistleblower protection lawsuit filed by former Risk Manager Jeannette Chavez. This payment was disclosed in a quarterly litigation report provided to the City Council last month.
Chavez alleged that city officials retaliated against her after she warned them about asbestos risks during the renovation of the former Lovelace hospital on Gibson and Madeira. The site was intended to become a homeless shelter and social services hub. Her suit claimed that high-level staff, under the direction of Mayor Tim Keller, created a hostile work environment following her warning.
New Mexico Environment Department findings from 2023 determined that workers, city employees, and residents were exposed to asbestos for nearly a year. The exposure window ran from April 11, 2022, to March 9, 2023, when construction halted. The department fined the city more than $760,000 and fined the project contractor, Consolidated Builders, approximately $330,000.
Chavez’s attorney, Edward Hollington, stated that his client sought to prevent harm to workers and the public. The lawsuit also alleged violations of the Fraud Against Taxpayers Act and argued that Chavez was forced to resign through retaliatory constructive discharge. She submitted her two-week notice on October 6, 2023, citing severe and pervasive harassment.
According to the complaint, Chavez alerted then-General Services Director John Craig and other senior staff to the asbestos one month before renovations stopped. Hollington said he remained bewildered that work continued after the warning. The complaint alleged that Craig and others became aggressive toward Chavez and her staff after she raised the issue.
Tensions reportedly increased after Chavez distributed notices of possible exposure to workers and the public. Then-Chief Administrative Officer Lawrence Rael allegedly told Chavez she sent out too many notices. The complaint further claimed that Rael and then-Chief Financial Officer Sanjay Bhakta yelled at Chavez and excluded her from budget meetings. It alleged she was pressured to spend departmental funds on unrelated projects.
A city spokesperson said in a statement that officials believed the claims lacked substantial merit. The statement explained that the city’s legal team determined the costs and resources required for trial would outweigh the benefits of continued litigation. Officials concluded that settling was in the city’s best interest.
Hollington responded by asking readers to decide for themselves, noting that the case obviously had merit. Several other lawsuits remain pending, alleging that workers unknowingly handled and improperly disposed of fireproofing material containing asbestos. The city previously sealed off a 4,000-square-foot area in April 2023 to prevent future exposure.